Question 10 of 12
A alone can do a job in 20 days. He works for 5 days, then B joins him and they finish the rest in 6 more days. How many days would B alone take for the whole job?
- A 12 days
- B 13 1/3 days
- C 15 days
- D 16 days
B. 13 1/3 days
Step 1: A's work in 5 days = 5/20 = 1/4
→ Step 2: remaining = 3/4
→ Step 3: together per day = (3/4) ÷ 6 = 1/8
→ Step 4: B per day = 1/8 − 1/20 = 3/40
→ Step 5: B alone = 40/3 = 13 1/3 days
→ Answer: 13 1/3 days