Question 12 of 12
Eight workers can finish a job in 12 days. After 4 days, 4 workers leave. How many days in total does the job take?
- A 24 days
- B 18 days
- C 16 days
- D 20 days
D. 20 days
Step 1: total work = 8 × 12 = 96 worker-days
→ Step 2: first 4 days use 8 × 4 = 32
→ Step 3: remaining = 64 worker-days
→ Step 4: 4 workers take 64 ÷ 4 = 16 days
→ Step 5: total = 4 + 16 = 20 days
→ Answer: 20 days